Safety and health in one of the works to widen the platform of the Provença station of the FGC

Provença Train Station

If you have passed through the center of Barcelona in recent years, it is very likely that you have noticed the occupation of the chamfers of Calle Balmes with Rosselló, extending to the building of the Universitat Pompeu Fabra. Perhaps it has given them the impression that the space has not been altered in all this time, because the bulk of the work is being carried out in the underground of the city, with the aim of extending the platform of the station of Provença

.

If they are also users of the station, from inside the platform they will not appreciate what is being done either, since the occupation has been minimal, since it is understood that there are large agglomerations of people at rush hour and decreasing the width of the platform could mean an increase in the risk in the areas not protected by the screens.

So what is this mysterious work that is nowhere to be seen, and on which they have been working for more than two years?

” width=

Protections to third parties in piloting work

It has been a complicated work to carry out in terms of safety, first of all because of its location, which has forced to restrict the occupation spaces as much as possible, despite the fact that the type of machinery to be used in the different phases was of considerable dimensions. In a first phase, micropiloting works were carried out on Balmes Street to reinforce the gables of the return of the station in the sections between the existing station and the new gallery section. For the execution of them, it was necessary to carry out a well-defined action protocol to guarantee mobility on the surface, and guarantee the safety of the users of the station inside. The drillings closest to the platform were made outside of opening hours to the public, and carrying out a thorough monitoring of the alignment of each of the micropiles to avoid possible deviations with the considerable risks they posed to workers and citizens.

Also, to reinforce the safety of station users, a series of sound-reducing protective panels reinforced with a metal structure were placed on the platform, which guaranteed, in the event of a detour, that the passenger area could not be accessed.

Sound absorbing protective panels reinforced with metal structure

In Rosselló Street, a screen of micropiles was made on the side closest to the buildings, for soil containment and to carry out the excavation of the emergency staircase, which on the paved side, already had the existing screen of the lobby and corridor that connects the Provença station of FGC with those of Diagonal of lines 3 and 5 of Metro.

In this way, the excavation and construction work of the ladder and structure to support the sewage collector of the adjoining farms were carried out safely. On the surface, in order to avoid the possible fall of personnel, the perimeter fencing of the different holes was available at all times, also protected with concrete barriers in the areas close to the circulation of vehicles, to prevent them from falling and running over construction personnel and pedestrians.

In order to reduce the impact of noise on neighbors, sound-reducing panel structures have been placed, enveloping the noisy elements such as electric generators or compressors. Even in the execution of demolition and cutting works, screens were placed near the focus to try to minimize the effect, while protecting against possible particle projections in the chopping process. Likewise, an acoustic record has been kept at all times to verify that the permissible sound levels were not exceeded

.

Another action was the placement of a net covering the vault of the station throughout the affected section, in order to prevent possible vibrations during the execution of the work from falling any piece of tile covering the vault, some of which had already been previously detached. A waterproof protective sheet was also placed in the section where piloting work was carried out to prevent the fall of water necessary in the process in case

it leaked.