news 08 January 2025

The civil works sector calls on the Government to urgently reform the exceptional price review

The limited effectiveness of the exceptional price review for works contracts signed before 2021 puts its execution at risk. This situation affects outstanding projects such as the four corridors of ADIF AV and key actions of the General Directorate of Roads, among others

.

The measures approved by the Government, such as RRDD-Law 3/2022, 6/2022, 14/2022 and Order HFP/1070/2022, were designed to guarantee the execution of public contracts and compensate construction companies for the unforeseen increase in costs. Despite the benefits brought, these measures are not sufficient to balance contracts awarded before 2021, especially since they exclude concepts such as energy and labor, and limit the revision to 20% of the award price

.

Builders are bearing real cost increases of between 27% and 55%, but can only receive a maximum compensation of 20%. This generates an unsustainable financial burden that directly affects the viability of almost 40 contracts, including the Murcia-Almería, León-Asturias, Madrid-Extremadura and Vitoria-San Sebastián corridors. This situation could delay or even paralyse essential public works financed with European PRTR funds.

To avoid these risks, the sector calls for specific reforms such as:

  • Reference the revision limit to the base tender budget or to the contract price, rather than the award price.
  • Increase the maximum revision limit from 20% to 30%.
  • Consider that contracts are in execution as long as obligations and rights persist, until the end of the warranty period.
  • These improvements would ensure the continuity and completion of the affected public works, while ensuring compliance with PRTR deadlines and protecting the public interest.